With previous versions of Solutionlink the ability to create a panel migration when upgrading from Sol 64 to Sol 6000 did not work.



With V2.3.1 this function now does.



In Solutionlink, select the panel profile and then Right Click on it with the mouse.


In the options that come up you can then Select either


  • Solution 6000


  • Solution 6000-IP


You will get a confirmation pop-up  "Do you wish to migrate the customer to ............... "  Solution 6000 or Solution 6000-IP  depending on what you have selected.


Click on YES


You will then see 2 profiles as per below for the panel details you had.



You will then be able to setup your panel settings / connection option's etc.